Project Timeline
| Project Timeline | |
|---|---|
| Public announcement of project | March 2009 |
| Commencing community consultation | April 2009 |
| Permitting and environmental approvals | March 2009 - March 2010 |
| Engineering | June 2009 - January 2012 (95% completion) |
| Construction contract arrangements finalised | February 2010 |
| Financial close | September 2010 |
| Field construction start | November 2010 |
| Mechanical completion | April 2013 |
| Startup begins | June 2013 |
| Full production | November 2013 |